The National Grid Corporation of the Philippines (NGCP) revealed a power interruption will take place on Sunday, April 8, which will affect the Central Negros Electric Cooperative, Inc. (Ceneco) Lag-asan substation.
Date: Sunday (April 8)
Reasons:
* NGCP will conduct replacement of the rotten poles and insulator covering Calumangan-San Enrique 69kV transmission line
* Preventive Maintenance Servicing of 10 MVA Power Transformer at Hacienda Hilangban, Brgy. Lag-asan, Bago City
* Replacement of rotten poles covering Hilangban Feeders 1 to 4 (HF1-4), Hilangban Substation, Hacienda Hilangban, Brgy. Lag-asan, Bago City
* Line clearing covering HF1 to 4
* Uprating of 69kV protection of Sum-ag substation and feeders
* Replacement of rotten poles covering Sum-ag Feeders 1 and 2 (SF1 & 2)
* Preventive Maintenance Servicing of 10MVA Power Transformer, Sum-ag Substation, Abuanan Road, Brgy. Sum-ag, Bacolod City
* Line clearing covering SF1 and 2
Schedule: From 6:00 a.m. to 5:00 p.m.
Affected Areas:
SF1 | From Sum-ag Substation to Sum-ag Highway, whole of Pta. Taytay Road including VMA, Sum–ag Highway to Medalla Elementary School near CEGASCO, Brgy. Pahanocoy, Pahanocoy Village (NHA Housing), Brgy. Road from BanggaTomaro to Brgy. Cabug and along Circumferential Road from Araneta down to HJR Prawn Processing, Boundary of Bago City and Bacolod City including Fiesta Homes Subd., Prk. KBS and San Sebastian Village up to Pta. Taytay Elementary School, Brgy. Firmville executive, Villa Maria Reyna South, BanggaTotong, Had. Edmar, Handumanan, Brgy. Felisa, Prk. Masan & Prk. Sta. Rita, Dulao, Prk. Tumpok & Prk. Overflow, Blumentritt
SF2 | From Sum-ag Substation along Abuanan Road (Sum-ag) to portion of Bago, Brgy. Tabunan, Brgy. Dulao, Brgy. Atipuluhanand Brgy. Abuanan, Sayson Piggery, Quiet Place Resort, GC&C Crusher, Prk. Sambag, Prk. Cadena de Amor, Prk. Rose 1 & 2
Schedule: From 7:00 a.m. to 5:00 p.m.
Affected Areas: Calumangan-San Enrique 69kV Transmission Line
HF1 | Portion of Brgy Lag-asan, Brgy. Balingasag, Bago City College, Prk. Kapahuan 1 & 2, Bago City Hospital, Prk. Santan, San Esteban Phase 2, Sta. Catalina Subdivision, Brgy. Sampinit, CF1, CF2, San Gabriel Subd., Villa Cristita, Carmella Homes, Prk. Camingawan, Prk. San Francisco, Brgy. Calumanggan, Prk. Flower, Prk. Paraiso, Brgy. Taloc, Prk, Newton, Cawayanan
HF2 | The whole area of Bago City including San Esteban Phase 1, Brgy. Poblacion, Pta. Playa, Prk. Batad, Prk. Malipayon, Baywalk
HF3 | Crossing Ubay, Bago Eco-Center, Humberto’s Resort, Hda. Pili, Brgy. Pacol, Brgy. Bagroy, Brgy. Sagasa, Brgy. Caridad, Brgy. Allanza, Brgy. Don Jorge Araneta (Central Ma-ao)
HF4 | Lag-asan relocation site, Brgy. Napoles, Brgy. Malingin, Crossing Mining, Brgy. Ma-ao, Villa Cresteta, Brgy. Bacong, Brgy. Binobuhan, Brgy. Mailum, Brgy. Ilijan, Viva Mineral Water, Buenos Aires Resort, Brgy. Manghumay, PNOC-EDC
Electricity consumers are further advised, in the event of any power interruption, electrical switches should be turned-off for safety reasons. When electricity supply resumes, please provide about 10 to 15 minutes before switching on all electrical appliances and facilities to avoid power surge. For inquiries, please call your Ceneco Call Center at telephone numbers 709-1256, 709-1257, and 435-3640 to 55 local 101,104,107, and 184. (PR)